Chief Secretary, Ladakh, Dr. Pawan Kotwal visited the Eastern portal of the Zojila Tunnel to review the ongoing progress of the project. The Chief Secretary was accompanied by SDM Drass, Vishal Atri.
During the visit, he interacted with the officers of NHIDCL, including the Project Manager MEIL, Col. A. K. Shiv Kumar, ICT Team Leader, Yousuf Es'hagpour, engineers, and on-site workers. He took a detailed assessment of the work.
He was informed that approximately 12 km of the tunnel has been completed, while nearly 1,200 meters remain under execution. The officials informed him that the breakthrough of Tunnel is expected by April next year.
The officials also briefed him on the tunnel’s ventilation and safety features, including the semi-transverse air-circulation system, as well as the various technical processes involved in tunnelling.
It was highlighted that the pace of work varies depending on the type of rock strata encountered, due to which progress sometimes accelerates and at other times slows down. He was further apprised that the target for project completion is February 2028.
Engineers also explained the challenges posed by the altitude and terrain of the Zojila axis, noting that an average of 2.5 to 3 meters of excavation is achieved per day, while the stitching and stabilization process requires additional time. They reiterated that, in case of emergencies involving critical patients, an early breakthrough by next April is expected to provide significant relief.
Dr. Kotwal appreciated the dedication and hard work of the workforce and encouraged them to achieve the breakthrough at the earliest for the benefit of the people of Ladakh. He noted that the Zojila Tunnel will be one of the longest and most challenging tunnels in the region, acknowledging the hardships faced by the people of Ladakh.
He also inspected the surveys conducted inside the tunnel and reviewed how the eastern and western portals are being aligned. Officers from Project Vijayak informed him that continuous measurements from advanced survey machines on both portals guide the precision and direction of the excavation work.
Overall, the visit proved highly productive, and Dr. Kotwal commended the efforts of the engineers and workers involved in this critical national project.
101
Report
हमें फेसबुक पर लाइक करें, ट्विटर पर फॉलो और यूट्यूब पर सब्सक्राइब्ड करें ताकि आप ताजा खबरें और लाइव अपडेट्स प्राप्त कर सकें| और यदि आप विस्तार से पढ़ना चाहते हैं तो https://pinewz.com/hindi से जुड़े और पाए अपने इलाके की हर छोटी सी छोटी खबर|
Advertisement
ACAshish Chauhan
FollowNov 21, 2025 07:34:100
Report
PKPushpender Kumar
FollowNov 21, 2025 07:33:490
Report
SPSanjay Prakash
FollowNov 21, 2025 07:33:300
Report
RRRAJA REHBER JAMAL
FollowNov 21, 2025 07:33:190
Report
HBHeeralal Bhati
FollowNov 21, 2025 07:33:050
Report
SCSUBIR CHATTERJEE
FollowNov 21, 2025 07:32:390
Report
AKAMAN KAPOOR
FollowNov 21, 2025 07:31:360
Report
AJAvinash Jagnawat
FollowNov 21, 2025 07:30:12Udaipur, Rajasthan:उदयपुर से बड़ी खबर, अमेरिकन अरबपति परिवार का शाही विवाह समारोह, शाही मेहमानों का लेकसिटी आने का दौर हुआ शुरू, सोफिया चौधरी पहुंची उदयपुर, बॉलीवुड सिंगर और डांसर है सोफिया
0
Report
28
Report
MKMANTUN KUMAR ROY
FollowNov 21, 2025 07:20:0962
Report
AVArun Vaishnav
FollowNov 21, 2025 07:19:4097
Report
NTNagendra Tripathi
FollowNov 21, 2025 07:18:1180
Report
JKJitendra Kanwar
FollowNov 21, 2025 07:17:3375
Report
MSMAYUR SHUKLA
FollowNov 21, 2025 07:17:1966
Report
SKSATISH KUMAR
FollowNov 21, 2025 07:17:0491
Report